Детали проекта

Общая информация

Название проекта

Yangtze River Green Ecological Corridor Comprehensive Agriculture Development Project - CS-TA-NPMO-2019-1 Recruitment of social specialist

Страновая программа/ План действий
Tender / Procurement notice
14 Фев 2020

Опубликован

14 Февраль 2020

Срок подачи

28 Февраль 2020

Бюджет

69 100 USD


Тип тендера


Индивидуальные консультанты

Номер

51116-002 Package CS-TA-NPMO-2019-1 Recruitment of social specialist

Донор

ADB - Азиатский банк развития (АБР)


Расчетная длительность

50 месяцы


Страны

Китай

Date Published: 14-Feb-2020 Deadline of Submitting EOI: 28-Feb-2020 11:59 PM Manila local time

Consultant Type Individual
Selection Method Individual Consultant Selection (ICS)
Source National
Technical Proposal Not Applicable

Selection Title Yangtze River Green Ecological Corridor Comprehensive Agriculture Development Project

Package Number CS-TA-NPMO-2019-1

Package Name Recruitment of social specialist

Advance Action No

Engagement Period 50 MONTH

Consulting Services Budget USD 69,100

Budget Type Maximum

Approval Number 3740
Approval Date 16-Nov-2018
Estimated Short-listing Date 01-Mar-2020
Estimated Commencement Date 16-Mar-2020
Open to non-Member Countries No

Additional Information

Possibility of contract extension Not known
Possibility of consideration for downstream assignment Not known
Indefinite Delivery Contract (IDC) No

Country of assignment China

Country of eligibility for national consultants Same as country of assignment

Contact Information

Project Officer Jianmin Li
Farmland Construction and Management Department, Ministry of Agriculture and Rural Affairs
Email ljm68468108@aliyun.com

Agencies

Primary Agency Country Agency Role Contact Person
Farmland Construction and Management Department, Ministry of Agriculture and Rural Affairs China Executing Agency

Cost Estimate

Cost Items Amount in USD
Remuneration and Other Expenses
All activities and inputs in the TOR but not limited to remuneration, per diem, air travel, miscellaneous travel expenses, report preparation, production, and transmission, land transportation, communications, etc.65,100
Contingency 4,000

TOTAL

69,100

Terms of Reference (Individual Consultant)

Expertise Social development monitoring
Expertise Group Agriculture/Rural Development
Consultant Source National
TOR Keywords Ethnic Minority, Social Development, Gender

Objective and Purpose of the Assignment

The specialist will assist in implementing and monitoring the project’s social components, including the
Ethnic Minority Development Plan (EMDP), Social Development Action Plan (SDAP) and the Gender Action
Plan (GAP).

Scope of Work

(i)Assist in implementing and monitoring the project’s social dimensions and safeguards to ensure that
the project is implemented in compliance with ADB requirements.
(ii)Assist the NPMO, PPMOs, and CPMOs in implementing, monitoring and reporting EMDP, GAP, SDAP, and
other relevant social measures.
(iii)Monitor these independently without involving in day-to-day implementation of the project.
(iv)Assist in the implementation of the project and report to the NPMO.

Detailed Tasks and/or Expected Output

Detailed Tasks:
(i)Maintain up-to-date information and database on implementation of EMDP, GAP, and SDAP through
document review, fieldwork and meetings;
(ii)Provide guidance to PMOs to develop detailed monitoring arrangements for EMDP, GAP, and SDAP;
(iii) Formulate and deliver training to focal staff of the NPMO, PPMOs, and CPMOs to monitor
implementation of the project’s SDAP, GAP, and EMDP;
(iv)Provide guidance to NPMO, PPMOs, and CPMOs maintain overall coordination for implementation of the
EMDP, SDAP, GAP, and relevant social measures;
(v)Provide guidance to NPMO, PPMOs, and CPMOs to implement the grievance redress mechanism (GRM) and to resolve any problems or grievances that are related to social dimensions or safeguards during the project implementation;
(vi)Undertake periodic monitoring and prepare monitoring reports on social aspects, including
implementation of EMDP, SDAP, and GAP (with a good quality of reports meeting ADB standards);
(vii)Assist the NPMO in compiling and submitting monitoring reports to ADB and address any comments from ADB;
(viii)Ensure through monitoring that the grievance redress mechanism is functioning well, and issues
identified during the monitoring are resolved on a timely manner; and
(ix)Undertake monitoring of other relevant social issues, as needed, and guide the NPMO, PPMOs, and
CPMOs to resolve relevant issues.
Output/Reporting Requirements:
Social monitoring report, including EMDP implementation progress and report, GAP, SDAP implementation
progress and report, be submitted to ADB, using the template agreed with ADB in March and September every year.

Minimum Qualification Requirements

(i)A doctor degree or higher in social science or related field;
(ii)At least 8 years of experience in social development and safeguards;good at sampling survey and data
collection;can use statistical or quantitative methods to study economic and social issues and evaluate performance;have published relevant articles and works;
(iii)Familiarity with ADB projects and ADB’s social development and safeguards policies;
(iv)Proficiency in spoken and written English, including an ability to prepare reports meeting ADB requirements;
(v)Obtained the National Natural Science Fund of China or the National Social Science Fund of China
project funding and served as the project manager; or obtained the key project or the major project of
the National Natural Science Fund or the National Social Science Fund, and served as the host or the sub-
topic host is preferred in the field of rural social and economic development research.

Minimum General Experience 8 Years
Minimum Specific Experience (relevant to assignment) 8 Years
Regional/Country Experience Required

Schedule and Places of Assignment (chronological and inclusive of travel)

Schedule Type Intermittent
Max. Working Days/Week Home Office 6 Field 5

City and Country Working Days Estimated Start Date Estimated End Date
Hunan, China 15 01-Apr-2020 17-Apr-2020
Beijing, China 15 29-Jun-2020 17-Jul-2020 Guizhou
Sichuan, China 15 01-Jul-2021 17-Jul-2021
Home Office, Other 60 01-Mar-2022 31-May-2022
Yunnan, China 15 01-Jun-2022 17-Jun-2022
Chongqing, China 15 01-Aug-2023 17-Aug-2023
Hubei, China 15 04-Mar-2024 20-Mar-2024

Total 150

Hyperlinks to Related Project Dossiers:

GPN
http://www.assortis.com/en/members/bsc_view.asp?id=472377&DataType=busop