Détails du projet

Vue d'ensemble

Titre du projet

VELIKA GORICA WATER (SPL 20140375

Early intelligence
8 nov 2019

Publié

8 novembre 2019

Budget

 


Type d'approvisionnement

Services , Equipements, Emplois

Référence

EIBZ251914

Bailleur de fonds

EIB - Banque européenne d'investissement


Pays

Croatie

VELIKA GORICA WATER (SPL 20140375

Reference: 20180728

Promoter – Financial Intermediary

REPUBLIC OF CROATIA

Location
Croatia
Description

The project covers the Velika Gorica agglomeration, located a few kilometres south of Zagreb. The main objectives of the project are to achieve compliance with the Urban Wastewater Directive and the Water Framework Directive in minimizing discharges of wastewater pollutants by extending and rehabilitating the existing sewer network and constructing a tertiary wastewater treatment plant. The project has been reviewed by JASPERS.

Objectives

The project will contribute to environmental protection and natural resource efficiency.

Sector(s)
Industry - Construction

Proposed EIB finance (Approximate amount)

EUR 6 million

Total cost (Approximate amount)

EUR 52 million

Environmental aspects

The project's components will contribute to ensure compliance with key EU directives in the water sector notably the Urban Waste Water Treatment Directive (91/271/EC) and the Water Framework Directive (2000/60/EC). Where and if applicable, the requirements of the Environmental Impact Assessment (EIA) Directive 2011/92/EU as amended by 2014/52/EU and Strategic Environmental Assessment (SEA) Directive 2001/42/EC will be respected. The promoter will in such case, prior to utilising any EIB funds, be responsible for transmitting to the Bank the non-technical summary of the EIA. For any part of the project that may impact on a nature conservation site, the promoter will be required to provide to the Bank an approval of the competent authority and information on the mitigating measures required to comply with the Habitats Directive 92/43/EEC.

Procurement

The Bank will require the promoter to ensure that contracts for the implementation of the project will be tendered in accordance with the relevant applicable EU procurement legislation (Directives 2014/23/EU, 2014/24/EU or 2014/25/EU, where applicable, as well as Directives 92/13/EEC and 89/665/EEC) as interpreted by the Court of Justice of the European Union, with the publication of tender notices in the Official Journal of the European Union (OJEU), as and where required.