Project Performance Evaluation Report: Lao PDR-GMS Nam Theun 2 Hydroelectric Project - Economic Analysis Consultant

Programme National / Plan d'Action
Tender / Procurement notice
14 aoû 2019

Publié

14 août 2019

Date limite

20 août 2019

Budget

3 800 USD


Type d'approvisionnement


Consultants indépendants

Référence

SC 113134 LAO

Bailleur de fonds

ADB - Banque Asiatique de Développement, WB - Banque Mondiale


Durée estimée

5 mois


Pays

Laos

Date Published: 14-Aug-2019 Deadline of Submitting EOI: 20-Aug-2019 11:59 PM Manila local time

Selection Profile

Consultant Type Individual
Selection Method Individual Consultants Selection (ICS)
Source International
Technical Proposal Not Applicable

Selection Title Project Performance Evaluation Report: Lao PDR-GMS Nam Theun 2 Hydroelectric Project - Economic Analysis Consultant

Engagement Period 5 MONTH

Open to non-Member Countries No

Additional Information
Possibility of contract extension Not known
Possibility of consideration for downstream assignment Not known
Indefinite Delivery Contract (IDC) No

Country of assignment Lao People's Democratic Republic

Contact Information
Project Officer Houqi Hong
Designation Senior Evaluation Specialist
Asian Development Bank
Email hhong@adb.org

Publishing History

Type Publication Date Published By Duration of Advertisement Deadline
Original 14-Aug-2019 Michelle Angieline F. Dantayana 7 DAYS 20-Aug-2019

Cost Estimate

Cost Items Amount in USD

Remuneration and Other Expenses
All activities and inputs in the TOR but not limited to remuneration, per diem, air travel, miscellaneous travel expenses, report preparation, production, and transmission, land transportation, communications, etc. 3,601
Contingency 199

TOTAL
3,800

Terms of Reference

Expertise Economic Analysis

Expertise Group Economics/Financial Analysis
TOR Keywords economic, analysis, evaluation

Source International

Objective and Purpose of the Assignment

The Independent Evaluation Department (IED) of the Asian Development Bank (ADB) together with the
Independent Evaluation Group (IEG) of the World Bank Group (WBG) is undertaking a coordinated Project
Performance Evaluation Report (PPER) of the Greater Mekong Subregion (GMS) Nam Theun 2 Hydroelectric
Power Project (NT2 Project) in the Lao People’s Democratic Republic, which was financed by the Asian
Development Bank, the World Bank, and other donors and financial institutions. The Project was financed
using a combination of loan facilities amounting to about $900 million, and shareholders’ equity of
about $350 million. ADB financing included a $20 million public sector loan to the Government, a direct
loan to Nam Theun 2 Power Company Limited (NTPC) without Government guarantee of up to $50 million, and
a political risk guarantee for up to $50 million to mobilize commercial debt. The evaluation will be
conducted jointly with the Independent Evaluation Group (IEG) of the World Bank Group.

The PPER will be undertaken by a team consisting of: (i) a senior evaluation specialist as team leader;
(ii) a PPER consultant; (iii) a social specialist consultant (to be hired by IEG), (iv) an environmental
specialist consultant, (v) an economic analysis consultant, and (vi) a coordination
consultant/interpreter.

Scope of Work

The economic analysis consultant is expected to carry out a recalculation of the economic and financial
rates of return of the Project by applying cost-benefit analysis method adopted at the project design
stage, based primarily on data used in the economic and financial analysis for the project completion
report (PCR). Before the field evaluation mission, expected to be conducted by other team members in the
second half of September, the consultant will review the data and prepare a list of additional
data/information that the mission can help collect in the field.

The economic analysis consultant will be recruited intermittently for 5 working days from September to
December 2019 and 1 working day for January 2020. S/he will report to the team leader and coordinate
with the PPER consultant and will remain available as an advisory resource through the review and
consultations process until publication of the PPER.

Detailed Tasks and/or Expected Output

The expected outputs will be a draft report/relevant PPER sections based on IED guidelines for public
sector evaluation and IED guidelines for private sector evaluation and based on comments from the team
leader, assessing the Project’s economic and financial viability to validate or update the results of
the economic analysis presented in the project completion report.

Minimum Qualification Requirements

The consultant should have a background in economics, evaluation, energy and environmental sectors, or
related fields, with prior work experience in evaluating energy projects. He/she should also have strong
knowledge and experience in performing economic and financial analysis of projects, particularly
calculating internal rate of returns. Prior country experience in Lao PDR is an advantage.

Minimum General Experience 15 Years
Minimum Specific Experience (relevant to assignment) 8 Years
Regional/Country Experience Desired

Schedule and Places of Assignment (chronological and inclusive of travel)

Schedule Type Intermittent

Max. Working Days/Week Home Office 5
Field 6

City and Country Working Days Estimated Start Date Estimated End Date
Home Office, Other 5 02-Sep-2019 31-Dec-2019

Total
5